When do I register the PV system?
You register a PV system with storage with the grid operator before it is installed. § 19(3) NAV (Niederspannungsanschlussverordnung, the German Low Voltage Connection Ordinance) requires this for every customer-owned generating installation. The grid operator checks whether the grid and the service connection can take the feed-in and specifies the metering set-up.
Your electricity bill shows which grid operator is responsible for your PV system. Within the city of Munich it is SWM Infrastruktur; in many municipalities of the Munich district (Landkreis München) it is Bayernwerk Netz. Both accept registrations through an online portal.
The battery is part of the PV system's registration, because it can both feed electricity into the grid and draw from it. If it is retrofitted later, the contractor registers it separately. SWM Infrastruktur has its own procedure for retrofitting battery storage.
- The electrical contractor registers the system and the battery, with data sheets, in the grid operator's portal.
- The grid operator reviews the registration and approves the feed-in or sets conditions.
- The contractor installs the system and applies for grid commissioning, with a meter change if needed.
- The contractor submits the commissioning report to the grid operator.
Note: Connection and commissioning on the grid are carried out by an electrical contractor listed in a grid operator's register of approved installers. Work on the meter cabinet and the building installation is not a job for non-specialists.
How do I register in the Marktstammdatenregister?
A new PV system must be entered in the Bundesnetzagentur's Marktstammdatenregister (the Federal Network Agency's register of energy installations) within one month of commissioning (§ 5(5) MaStRV). Registration is also possible at the planning stage. It is the obligation of the system operator, which usually means you.
The solar system and the battery are two units and are registered separately. In the online form you can enter the battery together with the solar system or add it later. A retrofitted battery therefore needs its own entry, even if the solar system is already in the register.
If registration in the Marktstammdatenregister is missing, the grid operator may withhold the feed-in tariff. Under § 52 EEG (Erneuerbare-Energien-Gesetz, the German Renewable Energy Sources Act), a payment of €10 per kilowatt per month may also be due, which falls to €2 once the registration has been made.
How much is the feed-in tariff?
The feed-in tariff for a PV system depends on the date of commissioning and then applies for 20 years. The Bundesnetzagentur publishes the rates, which fall every six months.
| Capacity | Partial feed-in | Full feed-in |
|---|---|---|
| up to 10 kW | 7.70 ct/kWh | 12.22 ct/kWh |
| over 10 to 40 kW | 6.66 ct/kWh | 10.24 ct/kWh |
Note: The rates are based on the EEG 2023, which applies to systems commissioned up to 31 December 2026. According to the Bundesnetzagentur, a successor regulation for the period after that is under parliamentary deliberation, as of 31 October 2026.
With a battery, partial feed-in is usual: you use the electricity yourself and feed in only the surplus. If you want the higher tariff for full feed-in, you must notify the grid operator before commissioning or, in each case, by 30 November of the preceding year.
If you later switch from full feed-in to self-consumption without notifying the operator, SWM Infrastruktur states that it charges €2 per kilowatt per month for the entire calendar year. So report such changes in good time.
What does the Solarspitzengesetz change?
The Solarspitzengesetz (Solar Peak Act) introduces two new rules for PV systems commissioned on or after 25 February 2025. Older systems are not affected. They can switch voluntarily and then receive 0.6 ct/kWh more once a smart meter (intelligentes Messsystem) has been installed.
- 60% limit: as long as no smart meter with control equipment is installed, a system below 100 kW that receives a feed-in tariff may feed in at most 60 per cent of its installed capacity (§ 9(2) EEG). The limit applies to power, not to the amount of energy.
- Negative prices: no tariff is paid during periods with a negative spot market electricity price (§ 51 EEG). For systems below 100 kW this applies from the year after a smart meter is installed.
- Compensation: under § 51a EEG, the quarter-hours without a tariff are added proportionally to the end of the tariff period.
A battery helps with both rules of the Solarspitzengesetz: it absorbs midday peaks that would otherwise be curtailed and supplies the electricity to the building in the evening. An energy manager can also shift a wallbox or heat pump into the midday hours.
Note: As of 31 October 2026. The installation of smart meters and the control rules are currently being rolled out step by step. Check your grid operator's current requirements before commissioning.
Is VAT charged on the system and battery?
No. Supply and installation of a PV system with battery storage are usually subject to 0% VAT. § 12(3) UStG (German VAT Act) sets this out for solar modules, essential components and batteries that store the solar electricity. The condition is that the system is on or near residential buildings or certain public buildings.
For a PV system with a capacity of no more than 30 kW according to the Marktstammdatenregister, these conditions are deemed to be met. A battery retrofitted later also qualifies for the zero rate if it stores electricity from the solar system. Correct registration is therefore also important for tax purposes.
What the contractor checks before registration
Before registering a PV system with storage, the electrical contractor checks whether the meter cabinet and service connection can accommodate the system. This includes space for a bidirectional meter or a smart meter, the location of the battery and the cable route from the roof to the inverter.
The following information helps with planning:
- your annual electricity consumption according to your latest bill
- planned loads such as a wallbox or heat pump
- whether you want partial or full feed-in
- for rented property or an owners' association: the owner's consent or the association's resolution
For grid registration, the contractor compiles the data sheets for the modules, inverter and battery. After commissioning you receive the report and technical data you need to enter the system and the battery in the Marktstammdatenregister. Reinlicht Elektrotechnik is an electrical contractor based in Taufkirchen and is listed in the registers of approved installers of the grid operators in our service area.