Do I have to replace my meter cabinet?
You do not have to replace a meter cabinet just because of its age. No law requires it. As long as you change nothing and the installation is safe, the meter position may stay. This is known as protection of existing installations (Bestandsschutz). It ends with defects that endanger safety: under § 15 of the Niederspannungsanschlussverordnung (NAV, the German Low Voltage Connection Ordinance), the grid operator may inspect the installation, must point out such defects and can require them to be remedied.
An alteration also changes the situation. Under the application rule VDE-AR-N 4100, the technical rule for connections to the low-voltage grid, the current requirements apply to extended or modified parts of the installation. The installer must check whether the meter position has to be adapted. Typical triggers are:
- more power drawn from the grid or more feed-in
- continuous current instead of normal household load, for example from a wallbox or heat pump
- retrofitting a controllable consumer device under § 14a EnWG (Energiewirtschaftsgesetz, the German Energy Industry Act)
- a photovoltaic system or a battery that feeds into the grid
- a change in how rooms are used
- conversion from a single-phase to a three-phase connection
- a change of the network earthing system
Note: Under § 13 of the Niederspannungsanschlussverordnung, the connection owner (Anschlussnehmer), usually the property owner, is responsible for the installation behind the service fuse. Apart from the grid operator, work on it may only be carried out by an installation company listed in a grid operator's register of approved installers.
Which meter positions may still be used?
Whether an existing meter position may continue to be used after a change is governed by a table in the federal model text of the Technische Anschlussbedingungen (TAB 2023, technical connection conditions). The Forum Netztechnik im VDE (VDE FNN) explains it in an advisory note. The table covers three common changes: increased power, conversion to three-phase current and changed operating conditions such as a generating installation or charging point. Open meter boards are excluded in every case.
| Existing meter position | Can it still be used? |
|---|---|
| Meter board to DIN 43853 (from 1961), including with protection class II or upstream fuse | no |
| Meter cabinet to DIN 43870 with isolating device in the installation-side connection compartment | yes, subject to the grid operator's requirements and meter position wiring of at least 10 mm² |
| Meter cabinet to DIN 43870 with NH fuse in the grid-side connection compartment | yes, subject to the grid operator's requirements and meter position wiring of at least 10 mm² |
| Meter cabinet to DIN 43870 with selective main circuit breaker (SH switch) | yes |
| Meter cabinet to DIN VDE 0603 and VDE-AR-N 4100 | yes |
Even a formally suitable meter cabinet must be in proper condition. The qualified electrician inspects it on site for damage, damaged insulation, undersized conductor cross-sections and the appropriate degree of protection.
What warning signs does an old meter cabinet show?
An old meter cabinet shows some typical warning signs that you can spot from the outside without tools. Not every one of them means the whole cabinet has to be replaced. But they do show that a qualified electrician should look at the meter position before new large loads are added. If, for example, there is no residual current device (RCD), DIN VDE 0100-410 has required this additional protection for new and modified socket-outlet circuits up to 32 A since its 2018 edition.
- The meter is mounted on an open board without an enclosed cabinet.
- The fuse box contains only screw-in fuses, often a sign of an old installation with no spare capacity.
- There is no residual current device (RCD).
- There is no space for another meter or for the additional applications compartment that houses control and communication equipment.
- Cables are discoloured, covers are missing or there is a smell of burning.
- Fuses trip as soon as several large loads run at the same time.
Note: Discolouration, a smell of burning or heat at the meter cabinet is an emergency. Do not open the cabinet yourself; call a qualified electrician.
Does a smart meter need a new meter cabinet?
A smart meter does not automatically need a new meter cabinet. The existing meter position can often continue to be used; it depends on the installation. The metering point operator must install a smart meter (intelligentes Messsystem) where annual consumption exceeds 6,000 kWh on average over the last three years, for a photovoltaic system above 7 kW and for controllable installations such as a heat pump or wallbox that went into operation after 1 January 2024.
The metering point operator installs the meter and the gateway. If the meter cabinet has to be modified for this, the property owners bear these costs themselves.
Note: As of 31 October 2026: the rules on the smart meter rollout and the price caps are being adjusted continually. Your metering point operator's information is authoritative.
The process with the grid operator
When a meter cabinet is replaced, the local grid operator determines which Technische Anschlussbedingungen (TAB) apply. For the Munich city grid this is SWM Infrastruktur; depending on the municipality in the surrounding area, it is for example Bayernwerk Netz. Both currently refer to the TAB 2023 with their own supplements. In July 2026 the BDEW published a new model text (TAB 2026), which the grid operators are adopting, according to their own announcements.
- Site visit: the contractor inspects the meter position, main supply cable and distribution board and clarifies what needs to be adapted.
- Registration: a contractor listed in the register of approved installers registers the project with the grid operator, for example together with a wallbox, heat pump or photovoltaic system.
- Disconnection and seal: parts of the installation carrying unmetered electricity are sealed by the grid operator. For the alteration, the installation is de-energised.
- Alteration: the new meter cabinet is installed and connected in accordance with the TAB and VDE-AR-N 4100.
- Testing: the installer tests the modified installation to DIN VDE 0100-600 and documents the readings.
- Commissioning: the registered contractor applies for commissioning. The metering point operator installs the meter, and the grid operator can re-seal the parts carrying unmetered electricity.
SWM Infrastruktur states that it expects around 10 working days from the complete online application to commissioning. Other grid operators have their own time frames.
Note: If the meter cabinet is in the stairwell of an apartment building, fire safety requirements of the Leitungsanlagenrichtlinie (guideline on fire safety for cable installations) may prevent an extension at that location. The contractor clarifies this with the competent authority.
What do the costs depend on?
The cost of a new meter cabinet depends mainly on how much behind the meter has to be renewed as well. According to Stiftung Warentest, the Verbraucherzentralen (consumer advice centres) point out that, together with alterations to the wiring, a new meter cabinet can easily cost several thousand euros. The costs are borne by the property owners. These factors determine the effort involved:
- Main supply cable: whether the cable from the service connection to the meter cabinet is sufficient for the new load or has to be relaid.
- Meter positions: how many positions are needed, for example for the household, heat pump, wallbox or communal supply in an apartment building.
- Space for the smart meter: whether the additional applications compartment for the gateway and control equipment is available.
- Selectivity: whether a selective main circuit breaker (SH switch) has to be retrofitted upstream of the meters, which disconnects only the affected part in the event of a fault.
- Distribution: new residual current devices and surge protection in the downstream circuits.
- Location and construction: whether the cabinet has to be moved for fire safety reasons and how many wall openings and cable routes are needed.
Note: The figure of several thousand euros is a guide value from the Verbraucherzentralen, cited by Stiftung Warentest, as of September 2026. A reliable price comes from a quote after a site visit.
Site visit: what is checked
At the site visit for the meter cabinet, the qualified electrician determines whether the existing meter position may continue to be used under the TAB table or has to be replaced. Reinlicht Elektrotechnik is an electrical contractor based in Taufkirchen and is listed in the registers of approved installers of the grid operators in our service area, so it can submit the registration to the grid operator itself.
- Type of meter position and fuses, cross-section of the meter position wiring and of the main supply cable
- Condition of insulation, covers and terminals, signs of overheating
- Free space for additional meters and the additional applications compartment
- Location of the cabinet and fire safety, especially in the stairwell
Where available, have the following information ready: names of the grid operator and metering point operator, meter number from your latest electricity bill, planned devices with their power ratings, such as a wallbox, heat pump or photovoltaics, and earlier test reports. If the cabinet smells of burning or feels warm, that is not a case for an appointment but an emergency: the 24/7 emergency service is available on the mobile number, charged separately as an additional service.